Merged data

The merged procurement sheet (PR → PO → GRPO) with the realisasi status used by KPI 2/3 · 13,488 row(s)

Export CSV
How the three files are consolidated— click to expand

Three SAP exports are combined. The SPINE is PR TO PO TO GRPO — the master PR list (one row per PR-item, including PRs not yet converted to a PO). It sets the dashboard's date span and is KPI 4's denominator.

PO.csv enriches it with the PO details that only it carries: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), the ETA, currency and unit price, joined on PO No.

LEAD TIME PR TO GR adds the goods-receipt detail: one row per GR with its date and quantity, plus the ordered PO quantity, last/current price and PR→PO days. This is what makes the quantity-aware completion possible.

KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).

On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality), 6 (Substitution) and 7 (New Vendor) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.

Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.

PR NoPR DateItem GroupItem CodeItemLast POLast PricePO NoPO Date ▼ETAQtyPricePR→POGRPO NoGRPO DatePO→GRPODeadlineRealisasi
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103662026-04-202026-04-27On time
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103672026-04-202026-04-27On time
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103682026-04-202026-04-27On time
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532605101122026-05-07172026-04-27Late
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103712026-04-202026-04-27On time
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103652026-04-202026-04-27On time
2604100472026-04-17BAHAN BAKU BODY1010.0039BENTONITE CBP2606101443852604101072026-04-202026-04-20237,26038532604103702026-04-202026-04-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605006672026-05-21332026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605008732026-05-28402026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582606006542026-06-17602026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605007682026-05-23352026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582606000302026-06-02452026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582606000732026-06-03462026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605001782026-05-07192026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582606002612026-06-08512026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605005222026-05-16282026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605004252026-05-13252026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582606004642026-06-12552026-05-27Late
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605000472026-05-04162026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605004682026-05-15272026-05-27On time
2601007302026-02-19BAHAN PEMBANTU2045.0004PALLET LOKAL SETENGAH BARU 95*110*1126040033425,0002604003342026-04-182026-05-205,00025,000582605007972026-05-25372026-05-27On time
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242605003742026-05-12242026-05-09Late
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242605000922026-05-05172026-05-09On time
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242605002222026-05-08202026-05-09On time
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242605001312026-05-06182026-05-09On time
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242026-05-09Overdue
2603003662026-03-25BAHAN PEMBANTU2045.0006PALLET EXPORT 95*110*13 CM26060011277,0002604003362026-04-182026-05-0250074,000242605004212026-05-13252026-05-09Late
2603004072026-03-27PERSEDIAAN UMUM6030.2825LIST U ALUMINIUM 1X1 P=6M26050042842,0002604003422026-04-182026-04-18575,000222026-04-25Overdue
2604001232026-04-10SPAREPART5017.0272LIMIT SWITCH OMRON (WLCA 12-2N-O)260400351215,0002604003512026-04-182026-04-303215,00082604009872026-04-2792026-05-07On time
2604001632026-04-13SPAREPART5012.01SEAL TC 35.62.72604005309,0002604003532026-04-182026-04-28159,00052604008212026-04-2242026-05-05On time
2604001632026-04-13SPAREPART5012.0075SEAL TC 30.42.72604005306,0002604003532026-04-182026-04-28156,00052604008212026-04-2242026-05-05On time
2604001632026-04-13SPAREPART5012.0118SEAL TC 45.62.92604003539,0002604003532026-04-182026-04-28159,00052604008212026-04-2242026-05-05On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042604010112026-04-28102026-05-04On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042604007902026-04-2242026-05-04On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042604009452026-04-2572026-05-04On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042604009052026-04-2462026-05-04On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042604008502026-04-2352026-05-04On time
2604001782026-04-14BAHAN PEMBANTU2045.0011PALLET LOKAL BARU 100*110 BALOK 426060024047,0002604003352026-04-182026-04-271,50047,00042606002962026-06-09522026-05-04Late
2604001822026-04-15PERSEDIAAN UMUM6050.174GELAS UKUR PLASTIK 5000ML ( 5 LITER )26040037174,1002604003712026-04-182026-04-27274,10032604007992026-04-2242026-05-04On time
2604001852026-04-15PERSEDIAAN UMUM6050.0994SEPATU BOOTS SIZE 41260400358160,0002604003582026-04-182026-04-281160,00032604009862026-04-2792026-05-05On time
2604001852026-04-15PERSEDIAAN UMUM6050.0995SEPATU BOOTS SIZE 42260400358160,0002604003582026-04-182026-04-281160,00032604009862026-04-2792026-05-05On time
2604001952026-04-15SPAREPART5030.1839AUTONIC TEMPERATURE CONTROL TC4S-14R260400368545,0002604003682026-04-182026-04-301545,00032026-05-07Overdue
2604001962026-04-15SPAREPART5019.0327GEAR REDUCER MNRV 050 RATIO 1:10 FLANGE 0.37KW B5 OUTPUT SHAFT 24MM2604003573,062,5002604003572026-04-182026-05-0213,062,50032604010862026-04-29112026-05-09On time
2604001962026-04-15SPAREPART5019.0368GEAR REDUCER MNRV 050 RATIO 1:100 FLANGE 0.37KW B5 OUTPUT SHAFT 24MM2604003573,062,5002604003572026-04-182026-05-0213,062,50032604010862026-04-29112026-05-09On time
2604001962026-04-15SPAREPART5019.0017GEAR REDUCER MNRV 050 RATIO 1:20 FLANGE 0.37KW B5 OUTPUT SHAFT 24MM2604003573,062,5002604003572026-04-182026-05-0213,062,50032604010862026-04-29112026-05-09On time
2604001982026-04-15SPAREPART5032.0903OIL FILTER C-115326040034859,5002604003482026-04-182026-04-30759,50032604008742026-04-2352026-05-07On time
2604001982026-04-15SPAREPART5032.1022FILTER FC 170726040034888,3002604003482026-04-182026-04-30788,30032604008742026-04-2352026-05-07On time
2604002022026-04-15PERSEDIAAN UMUM6050.0568ACCU KERING 105 D 31 R/L2605003332,350,0002604003542026-04-182026-04-2922,350,00032604008272026-04-2242026-05-06On time
2604002102026-04-15SPAREPART5030.1368REGULATOR ANGIN AR 2000260400352135,0002604003522026-04-182026-05-043135,00032604009902026-04-2792026-05-11On time
2604002172026-04-15SPAREPART5017.0448FAN PANEL 12X12 CM 24 VDC26040036980,0002604003692026-04-182026-04-30580,00032604011832026-04-30122026-05-07On time