Merged data
The merged procurement sheet (PR → PO → GRPO) with the realisasi status used by KPI 2/3 · 13,488 row(s)
How the three files are consolidated— click to expand
Three SAP exports are combined. The SPINE is PR TO PO TO GRPO — the master PR list (one row per PR-item, including PRs not yet converted to a PO). It sets the dashboard's date span and is KPI 4's denominator.
PO.csv enriches it with the PO details that only it carries: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), the ETA, currency and unit price, joined on PO No.
LEAD TIME PR TO GR adds the goods-receipt detail: one row per GR with its date and quantity, plus the ordered PO quantity, last/current price and PR→PO days. This is what makes the quantity-aware completion possible.
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality), 6 (Substitution) and 7 (New Vendor) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR No | PR Date | Item Group | Item Code | Item | Last PO | Last Price | PO No | PO Date ▼ | ETA | Qty | Price | PR→PO | GRPO No | GRPO Date | PO→GRPO | Deadline | Realisasi |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500319 | 2026-05-11 | 20 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500353 | 2026-05-12 | 21 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500465 | 2026-05-15 | 24 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500318 | 2026-05-11 | 20 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500317 | 2026-05-11 | 20 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500167 | 2026-05-07 | 16 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500265 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500266 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500316 | 2026-05-11 | 20 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500264 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500213 | 2026-05-08 | 17 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500215 | 2026-05-08 | 17 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500262 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500261 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500117 | 2026-05-06 | 15 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500082 | 2026-05-05 | 14 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500263 | 2026-05-09 | 18 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500081 | 2026-05-05 | 14 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500164 | 2026-05-07 | 16 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500119 | 2026-05-06 | 15 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500120 | 2026-05-06 | 15 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500118 | 2026-05-06 | 15 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500165 | 2026-05-07 | 16 | 2026-05-09 | On time |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500573 | 2026-05-19 | 28 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500574 | 2026-05-19 | 28 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500575 | 2026-05-19 | 28 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500529 | 2026-05-18 | 27 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500530 | 2026-05-18 | 27 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500531 | 2026-05-18 | 27 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500532 | 2026-05-18 | 27 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500504 | 2026-05-16 | 25 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500505 | 2026-05-16 | 25 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500506 | 2026-05-16 | 25 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500466 | 2026-05-15 | 24 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500576 | 2026-05-19 | 28 | 2026-05-09 | Late |
| 260400270 | 2026-04-17 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260400380 | 2026-04-21 | 2026-05-02 | 1,710,000 | 1,645 | 4 | 260500408 | 2026-05-13 | 22 | 2026-05-09 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500584 | 2026-05-19 | 28 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500728 | 2026-05-22 | 31 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500790 | 2026-05-25 | 34 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500875 | 2026-05-28 | 37 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500471 | 2026-05-15 | 24 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500422 | 2026-05-13 | 22 | 2026-05-11 | Late |
| 260400293 | 2026-04-20 | BAHAN PEMBANTU | 2045.0006 | PALLET EXPORT 95*110*13 CM | 260600112 | 77,000 | 260400382 | 2026-04-21 | 2026-05-04 | 1,000 | 74,000 | 1 | 260500541 | 2026-05-18 | 27 | 2026-05-11 | Late |
| 260410020 | 2026-04-08 | PERSEDIAAN UMUM | 6030.2884 | GERINDA TANGAN GA 7020 7INCH 2200W | 260410119 | 2,162,162.17 | 260410119 | 2026-04-21 | 2026-04-21 | 1 | 2,162,162.17 | 13 | 260410433 | 2026-04-22 | 1 | 2026-04-28 | On time |
| 260410020 | 2026-04-08 | PERSEDIAAN UMUM | 6050.0405 | GERINDA TANGAN 4 INCH MAKITA M0900B | 260410119 | 337,837.84 | 260410119 | 2026-04-21 | 2026-04-21 | 2 | 337,837.84 | 13 | 260410433 | 2026-04-22 | 1 | 2026-04-28 | On time |
| 260410020 | 2026-04-08 | PERSEDIAAN UMUM | 6050.1715 | CUTTING WHEEL 7 INC | 260410120 | 9,909.91 | 260410120 | 2026-04-21 | 2026-04-21 | 60 | 9,909.91 | 13 | 260410434 | 2026-04-22 | 1 | 2026-04-28 | On time |
| 260410045 | 2026-04-17 | PERSEDIAAN UMUM | 6030.2283 | BESI BETON POLOS U24 10MM SNI | 260610095 | 92,000 | 260410126 | 2026-04-21 | 2026-04-21 | 20 | 72,000 | 4 | 260410572 | 2026-04-30 | 9 | 2026-04-28 | Late |
| 260410051 | 2026-04-20 | BAHAN BAKU BODY | 1010.0044 | FELDSPAR LP-1 CRUSHER max KA 10% | 260410230 | 510 | 260410127 | 2026-04-21 | 2026-04-21 | 35,000 | 330 | 1 | 260410504 | 2026-04-27 | 6 | 2026-04-28 | On time |
| 260410051 | 2026-04-20 | BAHAN BAKU BODY | 1010.0046 | FELDSPAR LP-L LAPUKAN max KA 10% | 260410127 | 300 | 260410127 | 2026-04-21 | 2026-04-21 | 35,000 | 300 | 1 | 260410505 | 2026-04-27 | 6 | 2026-04-28 | On time |
| 260410051 | 2026-04-20 | BAHAN BAKU BODY | 1010.0045 | FELDSPAR LP-7 BATU max KA 10% | 260410230 | 470 | 260410127 | 2026-04-21 | 2026-04-21 | 35,000 | 310 | 1 | 260410503 | 2026-04-27 | 6 | 2026-04-28 | On time |