Consolidated data
LEAD TIME (PR → PO → GRPO) + realisasi, enriched with PO REPORT fields (currency, Lokal/Impor, vendor…) on the right · hover any column header (ⓘ) for its source · 13,431 row(s)
How the files are consolidated— click to expand
Report months follow the procurement cycle, not the calendar: report month M draws data from the 21st of (M-2) through the 20th of (M-1). For example January = 21 Nov–20 Dec, February = 21 Dec–20 Jan. KPI 1/2/3 window on PO date, KPI 4 on PR date, KPI 7 on vendor creation date.
LEAD TIME is the master sheet (PR → PO → GRPO, one row per PR-line, including PRs not yet converted to a PO). It sets the dashboard's date span, is KPI 4's denominator, and carries the goods-receipt detail: GR date and quantity, the ordered PO quantity, the PO Due Date (ETA), last/current price and PR→PO days.
PO REPORT enriches it with the PO detail that LEAD TIME lacks: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), plus ETA, currency and unit price, joined on PO No.
VENDOR LIST is the vendor master; KPI 7 counts Active vendors whose creation date falls in the window (cumulative per year, target 6).
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality) and 6 (Substitution) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR Noⓘ | PR Dateⓘ | Item Groupⓘ | Item Codeⓘ | Itemⓘ | Last POⓘ | Last Priceⓘ | PO Noⓘ | PO Date ▲ⓘ | ETAⓘ | ETA (PO Report)ⓘ | Qtyⓘ | Priceⓘ | PR→POⓘ | GRPO Noⓘ | GRPO Dateⓘ | PO→GRPOⓘ | Deadlineⓘ | Realisasiⓘ | L/Iⓘ | Currencyⓘ | Vendorⓘ | Vendor Codeⓘ | Status PRⓘ | Status POⓘ | Required Dateⓘ | Request Byⓘ | UoMⓘ | Total POⓘ | Outstandingⓘ | TOPⓘ | Remarksⓘ |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100677 | 2026-01-21 | 6 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260101105 | 2026-01-31 | 16 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260101040 | 2026-01-29 | 14 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100784 | 2026-01-23 | 8 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100720 | 2026-01-22 | 7 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260101495 | 2026-02-11 | 27 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260300490 | 2026-03-12 | 56 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260300040 | 2026-03-03 | 47 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260101518 | 2026-02-12 | 28 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260101496 | 2026-02-11 | 27 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100143 | 2026-01-14 | BAHAN BAKU BODY | 1010.0008 | BATU GAMPING (CA2) | 260500285 | 272 | 260100245 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 270,000 | 252 | 1 | 260300639 | 2026-03-16 | 60 | 2026-02-02 | Late | Lokal | IDR | CALSIUM BUMI MAKMUR CV. | S0451 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 68,040,000 | 0 | Net 30 | – |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260100787 | 2026-01-23 | 8 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260101038 | 2026-01-29 | 14 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260100589 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260100587 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260100586 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260100586 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260100897 | 2026-01-27 | 12 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260100897 | 2026-01-27 | 12 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260101038 | 2026-01-29 | 14 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0313 | AIR MINERAL BOTOL KECIL 220 ML | 260600248 | 19,819.82 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 60 | 19,369.37 | 2 | 260100787 | 2026-01-23 | 8 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PACK | 1,162,162.14 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN. DIKIRIM PARTIAL |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260100589 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260101192 | 2026-02-04 | 20 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100152 | 2026-01-13 | PERSEDIAAN UMUM | 6010.0351 | AIR MINERAL GALON | 260600248 | 18,018.02 | 260100265 | 2026-01-15 | 2026-01-31 | 2026-01-31 | 210 | 17,567.57 | 2 | 260100587 | 2026-01-19 | 4 | 2026-02-07 | On time | Lokal | IDR | SENTRALSARI PRIMASENTOSA PT. | S0086 | CLOSED | CLOSED | 2026-01-31 | Nanda Ayu Pratiwi | PCS | 3,689,189.28 | 0 | Net 30 | STOK AIR MINUM SELAMA 3 MINGGU DETAIL DILAMPIRKAN DIKIRIM PARTIAL SESUAI GALON YG KOSONG |
| 260100153 | 2026-01-13 | PERSEDIAAN UMUM | 6050.0034 | LPG 50 KG | 260600299 | 1,365,000 | 260100258 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 2 | 1,000,000 | 2 | 260101106 | 2026-01-31 | 16 | 2026-02-02 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-19 | Nanda Ayu Pratiwi | TBG | 2,000,000 | 0 | Net 60 | UNTUK MASAK AIR |
| 260100177 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0422 | BESI COR 12 MM | 260100255 | 99,000 | 260100255 | 2026-01-15 | 2026-01-20 | 2026-01-20 | 3 | 99,000 | 8 | 260100641 | 2026-01-20 | 5 | 2026-01-27 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | BTG | 297,000 | 0 | Net 60 | PENGECORAN TIANG GUDANG BATUBARA ATM 7.000 |
| 260100177 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0004 | SEMEN GRESIK 40KG | 260500241 | 59,500 | 260100255 | 2026-01-15 | 2026-01-20 | 2026-01-20 | 15 | 58,000 | 8 | 260100641 | 2026-01-20 | 5 | 2026-01-27 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | SAK | 870,000 | 0 | Net 60 | – |
| 260100177 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0049 | BESI COR 6 MM | 260100255 | 30,000 | 260100255 | 2026-01-15 | 2026-01-20 | 2026-01-20 | 2 | 30,000 | 8 | 260100641 | 2026-01-20 | 5 | 2026-01-27 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | BTG | 60,000 | 0 | Net 60 | PENGECORAN TIANG GUDANG BATUBARA ATM 7.000 |
| 260100177 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0001 | BATU CORAL | 260500241 | 400,000 | 260100255 | 2026-01-15 | 2026-01-20 | 2026-01-20 | 1 | 400,000 | 8 | 260100641 | 2026-01-20 | 5 | 2026-01-27 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | COLT | 400,000 | 0 | Net 60 | PENGECORAN TIANG GUDANG BATUBARA ATM 7.000 |
| 260100178 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0804 | AVIAN CLING SYNTHETIC 91 - KERAK ABU | 260300369 | 45,905.25 | 260100262 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 200 | 45,905.25 | 7 | 260101527 | 2026-02-12 | 28 | 2026-01-22 | Late | Lokal | IDR | TIRTAKENCANA TATAWARNA PT. | S0404 | CLOSED | CLOSED | 2026-01-14 | Nanda Ayu Pratiwi | KG | 9,181,050 | 0 | Net 30 | UNTUK PLATFORM AYAKAN DAN PLATFORM CONVEYOR |
| 260100178 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0804 | AVIAN CLING SYNTHETIC 91 - KERAK ABU | 260300369 | 45,905.25 | 260100262 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 200 | 45,905.25 | 7 | 260101029 | 2026-01-29 | 14 | 2026-01-22 | Late | Lokal | IDR | TIRTAKENCANA TATAWARNA PT. | S0404 | CLOSED | CLOSED | 2026-01-14 | Nanda Ayu Pratiwi | KG | 9,181,050 | 0 | Net 30 | UNTUK PLATFORM AYAKAN DAN PLATFORM CONVEYOR |
| 260100178 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0804 | AVIAN CLING SYNTHETIC 91 - KERAK ABU | 260300369 | 45,905.25 | 260100262 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 200 | 45,905.25 | 7 | 260101579 | 2026-02-13 | 29 | 2026-01-22 | Late | Lokal | IDR | TIRTAKENCANA TATAWARNA PT. | S0404 | CLOSED | CLOSED | 2026-01-14 | Nanda Ayu Pratiwi | KG | 9,181,050 | 0 | Net 30 | UNTUK PLATFORM AYAKAN DAN PLATFORM CONVEYOR |
| 260100178 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0917 | THINER A BIASA @ 5 LTR | 260500403 | 63,500 | 260100262 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 100 | 26,505.05 | 7 | 260101029 | 2026-01-29 | 14 | 2026-01-22 | Late | Lokal | IDR | TIRTAKENCANA TATAWARNA PT. | S0404 | CLOSED | CLOSED | 2026-01-14 | Nanda Ayu Pratiwi | LTR | 2,650,504.6 | 0 | Net 30 | UNTUK PLATFORM AYAKAN DAN PLATFORM CONVEYOR |
| 260100178 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0804 | AVIAN CLING SYNTHETIC 91 - KERAK ABU | 260300369 | 45,905.25 | 260100262 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 200 | 45,905.25 | 7 | 260101723 | 2026-02-18 | 34 | 2026-01-22 | Late | Lokal | IDR | TIRTAKENCANA TATAWARNA PT. | S0404 | CLOSED | CLOSED | 2026-01-14 | Nanda Ayu Pratiwi | KG | 9,181,050 | 0 | Net 30 | UNTUK PLATFORM AYAKAN DAN PLATFORM CONVEYOR |
| 260110004 | 2026-01-05 | PERSEDIAAN UMUM | 6050.1246 | KUNCI L SET ISKU | 260100548 | 90,000 | 260110096 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 2 | 68,932 | 10 | 260110374 | 2026-01-20 | 5 | 2026-01-22 | On time | Lokal | IDR | SHOPEE INTERNATIONAL INDONESIA. PT | S1043 | OPEN | CLOSED | 2026-01-12 | Tika Lisnawati | PCS | 137,864 | 0 | COD | REFF : 002/MRS/ENG/I/2026 KEBUTUHAN TOOLS SPD & SILO, ATAS PERMINTAAN ADITYA RAHMAN |
| 260110008 | 2026-01-07 | BAHAN BAKU GLAZE | 1098.0018 | ENGOBE UNDER TILE 210# | 260110103 | 2.5 | 260110103 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 24,000 | 2.5 | 8 | 260310283 | 2026-03-16 | 60 | 2026-01-22 | Late | Impor | RMB | SHIJIAZHUANG WONDERLAND TECHNOLOGY CO., LTD. | S0778 | CLOSED | CLOSED | 2026-02-14 | Aulia Safitri | Kg | 145,165,800 | 0 | - Cash Basic - | PERSIAPAN IMLEK DAN IDUL FITRI |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0291 | PLAT STRIP 3X30X6000 MM | 260110091 | 47,000 | 260110091 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 10 | 47,000 | 8 | 260110382 | 2026-01-20 | 5 | 2026-01-22 | On time | Lokal | IDR | GEMILANG JAYA BERSAMA, PT. | S0822 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | BTG | 470,000 | 0 | Net 45 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6030.2543 | PLAT ALUMUNIUM 0,8 (@25M/ROLL) | 260510025 | 4,348,000 | 260110100 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 60 | 4,200,000 | 8 | 260110403 | 2026-01-22 | 7 | 2026-01-22 | On time | Lokal | IDR | SRIHANA METALINDO ABADI,.PT | S0843 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | ROLL | 252,000,000 | 0 | Net 14 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6030.2542 | PLAT BAJA (1,2MX2,4MX3MM) | 260610225 | 852,800 | 260110091 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 450 | 695,000 | 8 | 260110382 | 2026-01-20 | 5 | 2026-01-22 | On time | Lokal | IDR | GEMILANG JAYA BERSAMA, PT. | S0822 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | LEMBAR | 312,750,000 | 0 | Net 45 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6030.2542 | PLAT BAJA (1,2MX2,4MX3MM) | 260610225 | 852,800 | 260110091 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 450 | 695,000 | 8 | 260110411 | 2026-01-22 | 7 | 2026-01-22 | On time | Lokal | IDR | GEMILANG JAYA BERSAMA, PT. | S0822 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | LEMBAR | 312,750,000 | 0 | Net 45 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6050.0088 | BESI UNP K.S U 120X6000 | 260110227 | 840,000 | 260110091 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 60 | 840,000 | 8 | 260110382 | 2026-01-20 | 5 | 2026-01-22 | On time | Lokal | IDR | GEMILANG JAYA BERSAMA, PT. | S0822 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | BTG | 50,400,000 | 0 | Net 45 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110014 | 2026-01-07 | PERSEDIAAN UMUM | 6030.0255 | SIKU 60X60X6000 MM | 260310039 | 336,000 | 260110091 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 20 | 325,000 | 8 | 260110382 | 2026-01-20 | 5 | 2026-01-22 | On time | Lokal | IDR | GEMILANG JAYA BERSAMA, PT. | S0822 | OPEN | CLOSED | 2026-01-14 | Tika Lisnawati | BTG | 6,500,000 | 0 | Net 45 | REFF : 005/MRS/ENG/I/2026 KEBUTUHAN DUCTING KILN PK02 B, ATAS PERMINTAAN KURNIA ADITYA |
| 260110019 | 2026-01-09 | SPAREPART | 5019.0336 | ROTOR GERINDA MERK:BOSCH TYPE:GWS 700 | 260110386 | 237,500 | 260110099 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 6 | 237,500 | 6 | 260110458 | 2026-01-27 | 12 | 2026-01-22 | Late | Lokal | IDR | TARUMA GITA PERSADA PT. | S0462 | CLOSED | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 1,425,000 | 0 | Net 45 | REFF : 007/PP/ENG/I/2025 KEBUTUHAN PABRIKASI PK02, ATAS PERMINTAAN RIPKI MAULANA, REPEAT ORDER PO 251210113 |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0151 | KABEL NYYHY 4X2.5 MM | 260600149 | 3,839,595 | 260110097 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 5 | 3,398,400 | 6 | 260110401 | 2026-01-22 | 7 | 2026-01-22 | On time | Lokal | IDR | PROVIDENCE NUSA ELECTRIC, PT | S1078 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | ROLL | 16,992,000 | 0 | Net 14 | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.075 | SKUN MCB 10MM | 260110098 | 900.9 | 260110098 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 100 | 900.901 | 6 | 260110426 | 2026-01-23 | 8 | 2026-01-22 | Late | Lokal | IDR | XAJERIKHO ABADI SEJAHTERA, PT | S1085 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 90,090.1 | 0 | - Cash Basic - | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0753 | SKUN MCB 2.5MM | 260110098 | 288.29 | 260110098 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 200 | 288.288 | 6 | 260110426 | 2026-01-23 | 8 | 2026-01-22 | Late | Lokal | IDR | XAJERIKHO ABADI SEJAHTERA, PT | S1085 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 57,657.6 | 0 | - Cash Basic - | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0486 | KABEL NYYHY 4X6MM (SUPREME) 100M/ROLL | 260110097 | 7,723,600 | 260110097 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 2 | 7,723,600 | 6 | 260110401 | 2026-01-22 | 7 | 2026-01-22 | On time | Lokal | IDR | PROVIDENCE NUSA ELECTRIC, PT | S1078 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | ROLL | 15,447,200 | 0 | Net 14 | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0748 | SKUN TEMBAGA SC10-8 | 260110098 | 900.9 | 260110098 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 100 | 900.901 | 6 | 260110426 | 2026-01-23 | 8 | 2026-01-22 | Late | Lokal | IDR | XAJERIKHO ABADI SEJAHTERA, PT | S1085 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 90,090.1 | 0 | - Cash Basic - | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0751 | SKUN MCB 16MM | 260110098 | 1,351.35 | 260110098 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 100 | 1,351.35 | 6 | 260110426 | 2026-01-23 | 8 | 2026-01-22 | Late | Lokal | IDR | XAJERIKHO ABADI SEJAHTERA, PT | S1085 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 135,135.1 | 0 | - Cash Basic - | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |
| 260110020 | 2026-01-09 | PERSEDIAAN UMUM | 6020.0749 | SKUN TEMBAGA SC16-8 | 260110098 | 1,351.35 | 260110098 | 2026-01-15 | 2026-01-15 | 2026-01-15 | 100 | 1,351.35 | 6 | 260110426 | 2026-01-23 | 8 | 2026-01-22 | Late | Lokal | IDR | XAJERIKHO ABADI SEJAHTERA, PT | S1085 | OPEN | CLOSED | 2026-01-16 | Tika Lisnawati | PCS | 135,135.2 | 0 | - Cash Basic - | REFF : 001/PP/ENG/I/2026 KEBUTUHAN INSTALASI ELECTRICAL RnD PK02, ATAS PERMINTAAN HELDI |