Consolidated data
LEAD TIME (PR → PO → GRPO) + realisasi, enriched with PO REPORT fields (currency, Lokal/Impor, vendor…) on the right · hover any column header (ⓘ) for its source · 13,431 row(s)
How the files are consolidated— click to expand
Report months follow the procurement cycle, not the calendar: report month M draws data from the 21st of (M-2) through the 20th of (M-1). For example January = 21 Nov–20 Dec, February = 21 Dec–20 Jan. KPI 1/2/3 window on PO date, KPI 4 on PR date, KPI 7 on vendor creation date.
LEAD TIME is the master sheet (PR → PO → GRPO, one row per PR-line, including PRs not yet converted to a PO). It sets the dashboard's date span, is KPI 4's denominator, and carries the goods-receipt detail: GR date and quantity, the ordered PO quantity, the PO Due Date (ETA), last/current price and PR→PO days.
PO REPORT enriches it with the PO detail that LEAD TIME lacks: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), plus ETA, currency and unit price, joined on PO No.
VENDOR LIST is the vendor master; KPI 7 counts Active vendors whose creation date falls in the window (cumulative per year, target 6).
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality) and 6 (Substitution) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR Noⓘ | PR Dateⓘ | Item Groupⓘ | Item Codeⓘ | Itemⓘ | Last POⓘ | Last Priceⓘ | PO Noⓘ | PO Date ▲ⓘ | ETAⓘ | ETA (PO Report)ⓘ | Qtyⓘ | Priceⓘ | PR→POⓘ | GRPO Noⓘ | GRPO Dateⓘ | PO→GRPOⓘ | Deadlineⓘ | Realisasiⓘ | L/Iⓘ | Currencyⓘ | Vendorⓘ | Vendor Codeⓘ | Status PRⓘ | Status POⓘ | Required Dateⓘ | Request Byⓘ | UoMⓘ | Total POⓘ | Outstandingⓘ | TOPⓘ | Remarksⓘ |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 260100044 | 2026-01-06 | SPAREPART | 5017.1063 | OMRON RELAY MY4-N24 VAC | 260100276 | 45,000 | 260100276 | 2026-01-15 | 2026-01-30 | 2026-01-30 | 10 | 45,000 | 9 | 260100876 | 2026-01-26 | 11 | 2026-02-06 | On time | Lokal | IDR | CENTRAL NUSA JAYA .PT | S0825 | CLOSED | CLOSED | 2026-01-10 | Nanda Ayu Pratiwi | PCS | 450,000 | 0 | Net 30 | SQUARING PN2 |
| 260100044 | 2026-01-06 | SPAREPART | 5017.106 | FUSE 5A 5X20 | 260100276 | 12,000 | 260100276 | 2026-01-15 | 2026-01-30 | 2026-01-30 | 20 | 12,000 | 9 | 260100876 | 2026-01-26 | 11 | 2026-02-06 | On time | Lokal | IDR | CENTRAL NUSA JAYA .PT | S0825 | CLOSED | CLOSED | 2026-01-10 | Nanda Ayu Pratiwi | PCS | 240,000 | 0 | Net 30 | STACKER PACKING PN1 |
| 260100044 | 2026-01-06 | SPAREPART | 5017.1061 | FUSE 10A 6X30 | 260100276 | 15,000 | 260100276 | 2026-01-15 | 2026-01-30 | 2026-01-30 | 20 | 15,000 | 9 | 260100876 | 2026-01-26 | 11 | 2026-02-06 | On time | Lokal | IDR | CENTRAL NUSA JAYA .PT | S0825 | CLOSED | CLOSED | 2026-01-10 | Nanda Ayu Pratiwi | PCS | 300,000 | 0 | Net 30 | STACKER PACKING PN1 |
| 260100044 | 2026-01-06 | SPAREPART | 5017.1064 | SOLENOID VALVE 4V210-08-AC24V | 260100276 | 107,000 | 260100276 | 2026-01-15 | 2026-01-30 | 2026-01-30 | 3 | 107,000 | 9 | 260100876 | 2026-01-26 | 11 | 2026-02-06 | On time | Lokal | IDR | CENTRAL NUSA JAYA .PT | S0825 | CLOSED | CLOSED | 2026-01-10 | Nanda Ayu Pratiwi | PCS | 321,000 | 0 | Net 30 | SQUARING PN2 |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0307 | PITA PRINTER LX 310 | 260610060 | 16,800 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 5 | 46,700 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PCS | 233,500 | 0 | Net 30 | UNTUK PRINT SURAT JALAN |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0192 | BUKU FOLIO 21.5*30.5 21.5 X 31.5 CM | 260600108 | 16,500 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 5 | 16,300 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PCS | 81,500 | 0 | Net 30 | UNTUK PROSES DAFTAR BARANG MASUK |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0148 | CUTTER BESAR L-500 | 260610151 | 7,767 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 1 | 12,000 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PCS | 12,000 | 0 | Net 30 | UNTUK PEMOTANGAN WAKTU ADA MUAT ECER |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0021 | COUNTINOUS FORM 3 PLAY 9 1/2 X 11 : 2 | 260600027 | 460,700 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 10 | 460,700 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | BOX | 4,607,000 | 0 | Net 30 | UNTUK PEMBUATAN SPM |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0153 | PENGGARIS BESI BESI/IRON, 30 CM | 260400206 | 6,000 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 3 | 6,700 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PCS | 20,100 | 0 | Net 30 | UNTUK MEMBUAT GARIS DIBUKU DMG |
| 260100081 | 2026-01-08 | PERSEDIAAN UMUM | 6010.0777 | CONTINUOUS FORM 5 PLAY 9 1/2 X 11 : 2 | 260100254 | 431,500 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 10 | 431,500 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | BOX | 4,315,000 | 0 | Net 30 | UNTUK PEMBUATAN SURAT JALAN |
| 260100081 | 2026-01-08 | PERSEDIAAN UMUM | 6010.0777 | CONTINUOUS FORM 5 PLAY 9 1/2 X 11 : 2 | 260100254 | 431,500 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 10 | 431,500 | 7 | 260101534 | 2026-02-12 | 28 | 2026-02-03 | Late | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | BOX | 4,315,000 | 0 | Net 30 | UNTUK PEMBUATAN SURAT JALAN |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0151 | ISI STAPLES KECIL #10 KECIL, NO.10-1M | 260610151 | 1,592 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 1 | 2,700 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PACK | 2,700 | 0 | Net 30 | BUAT ARSIP DOKUMEN |
| 260100081 | 2026-01-08 | STATIONERY | 6010.0156 | STAPLES KECIL HD-10 | 260610151 | 9,741 | 260100254 | 2026-01-15 | 2026-01-27 | 2026-01-27 | 3 | 34,500 | 7 | 260101000 | 2026-01-29 | 14 | 2026-02-03 | On time | Lokal | IDR | GADING MURNI, PT. | S0380 | OPEN | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | PCS | 103,500 | 0 | Net 30 | BUAT ARSIP DOKUMEN |
| 260100086 | 2026-01-08 | PERSEDIAAN UMUM | 6050.0459 | TENSIONER+SEALER | 260600133 | 720,721 | 260100251 | 2026-01-15 | 2026-01-30 | 2026-01-30 | 2 | 600,000 | 7 | 260100604 | 2026-01-19 | 4 | 2026-02-06 | On time | Lokal | IDR | YULI SETIAWAN SURABAYA, CV | S0524 | CLOSED | CLOSED | 2026-01-15 | Nanda Ayu Pratiwi | SET | 1,200,000 | 0 | Net 30 | UNTUK KEPERLUAN PENALIAN KERAMIK |
| 260100090 | 2026-01-08 | PERSEDIAAN UMUM | 6030.2551 | BESI SIKU STAINLESS STEEL 50X50X6000 MM | 260400532 | 1,115,315.32 | 260100263 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 2 | 1,171,171.17 | 7 | 260100796 | 2026-01-23 | 8 | 2026-02-02 | On time | Lokal | IDR | DASAN PUTRA PERKASA CV. | S0077 | CLOSED | CLOSED | 2026-01-10 | Nanda Ayu Pratiwi | BTG | 2,342,342.34 | 0 | Net 30 | TANGKI SLIP 1C |
| 260100092 | 2026-01-08 | PERSEDIAAN UMUM | 6030.0082 | OVERPAL | 260100270 | 10,000 | 260100270 | 2026-01-15 | 2026-01-20 | 2026-01-20 | 1 | 10,000 | 7 | 260100596 | 2026-01-19 | 4 | 2026-01-27 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-01-21 | Nanda Ayu Pratiwi | PCS | 10,000 | 0 | Net 60 | GUDANG PN2 |
| 260100123 | 2026-01-10 | SPAREPART | 5031.0934 | ROLL CONVEYOR OD 25MM X OD 60MM X 560MM X 700MM | 260100269 | 210,000 | 260100269 | 2026-01-15 | 2026-02-10 | 2026-02-10 | 20 | 210,000 | 5 | 260400389 | 2026-04-11 | 86 | 2026-02-17 | Late | Lokal | IDR | TRI STAR PERDANA TEKNIK .CV | S0600 | CLOSED | CLOSED | 2026-01-17 | Nanda Ayu Pratiwi | PCS | 4,200,000 | 0 | Net 30 | ROLL CONVEYOR SILO B & 1C |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101114 | 2026-01-31 | 16 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100855 | 2026-01-26 | 11 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100944 | 2026-01-28 | 13 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101113 | 2026-01-31 | 16 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101066 | 2026-01-30 | 15 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101184 | 2026-02-03 | 19 | 2026-01-31 | Late | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100722 | 2026-01-22 | 7 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100723 | 2026-01-22 | 7 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100680 | 2026-01-21 | 6 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101185 | 2026-02-03 | 19 | 2026-01-31 | Late | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100785 | 2026-01-23 | 8 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101282 | 2026-02-06 | 22 | 2026-01-31 | Late | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100581 | 2026-01-19 | 4 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100617 | 2026-01-20 | 5 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100618 | 2026-01-20 | 5 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100580 | 2026-01-19 | 4 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100679 | 2026-01-21 | 6 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100943 | 2026-01-28 | 13 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100893 | 2026-01-27 | 12 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100786 | 2026-01-23 | 8 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100856 | 2026-01-26 | 11 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100816 | 2026-01-24 | 9 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100987 | 2026-01-29 | 14 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100817 | 2026-01-24 | 9 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100892 | 2026-01-27 | 12 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101067 | 2026-01-30 | 15 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260101284 | 2026-02-06 | 22 | 2026-01-31 | Late | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100141 | 2026-01-13 | BAHAN BAKAR | 4020.0002 | BATU BARA ADB 6300 - 6500 | 260600262 | 1,750 | 260100241 | 2026-01-15 | 2026-01-24 | 2026-01-24 | 1,000,000 | 1,530 | 2 | 260100988 | 2026-01-29 | 14 | 2026-01-31 | On time | Lokal | IDR | HUAYAO ENERGI INDONESIA PT. | S0130 | CLOSED | CLOSED | 2026-01-20 | Qhadafy | KG | 1,530,000,000 | 0 | Net 45 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260101040 | 2026-01-29 | 14 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260101105 | 2026-01-31 | 16 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100981 | 2026-01-28 | 13 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100927 | 2026-01-27 | 12 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |
| 260100142 | 2026-01-14 | BAHAN BAKU BODY | 1010.0005 | PASIR KUARSA (LASEM) (HM JAYA) | 260600009 | 147 | 260100266 | 2026-01-15 | 2026-01-26 | 2026-01-26 | 1,000,000 | 140 | 1 | 260100808 | 2026-01-23 | 8 | 2026-02-02 | On time | Lokal | IDR | CV. HM JAYA PERKASA | S0545 | CLOSED | CLOSED | 2026-01-17 | Qhadafy | KG | 140,000,000 | 0 | Net 60 | – |