Consolidated data
LEAD TIME (PR → PO → GRPO) + realisasi, enriched with PO REPORT fields (currency, Lokal/Impor, vendor…) on the right · hover any column header (ⓘ) for its source · 13,431 row(s)
How the files are consolidated— click to expand
Report months follow the procurement cycle, not the calendar: report month M draws data from the 21st of (M-2) through the 20th of (M-1). For example January = 21 Nov–20 Dec, February = 21 Dec–20 Jan. KPI 1/2/3 window on PO date, KPI 4 on PR date, KPI 7 on vendor creation date.
LEAD TIME is the master sheet (PR → PO → GRPO, one row per PR-line, including PRs not yet converted to a PO). It sets the dashboard's date span, is KPI 4's denominator, and carries the goods-receipt detail: GR date and quantity, the ordered PO quantity, the PO Due Date (ETA), last/current price and PR→PO days.
PO REPORT enriches it with the PO detail that LEAD TIME lacks: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), plus ETA, currency and unit price, joined on PO No.
VENDOR LIST is the vendor master; KPI 7 counts Active vendors whose creation date falls in the window (cumulative per year, target 6).
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality) and 6 (Substitution) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR Noⓘ | PR Dateⓘ | Item Groupⓘ | Item Codeⓘ | Itemⓘ | Last POⓘ | Last Priceⓘ | PO Noⓘ | PO Date ▲ⓘ | ETAⓘ | ETA (PO Report)ⓘ | Qtyⓘ | Priceⓘ | PR→POⓘ | GRPO Noⓘ | GRPO Dateⓘ | PO→GRPOⓘ | Deadlineⓘ | Realisasiⓘ | L/Iⓘ | Currencyⓘ | Vendorⓘ | Vendor Codeⓘ | Status PRⓘ | Status POⓘ | Required Dateⓘ | Request Byⓘ | UoMⓘ | Total POⓘ | Outstandingⓘ | TOPⓘ | Remarksⓘ |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 260100780 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0026 | POTASSIUM FELDSPAR POWDER KN-200 | 260500316 | 2,720.56 | 260101148 | 2026-02-28 | 2026-04-01 | 2026-04-01 | 135,000 | 2,463.43 | 8 | 260500008 | 2026-05-02 | 63 | 2026-04-08 | Late | Lokal | IDR | BIOTA INDONESIA PT. | S0024 | OPEN | OPEN | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 332,563,050 | 350 | Net 45 | Acuan kurs BI: 16,758 |
| 260100780 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0026 | POTASSIUM FELDSPAR POWDER KN-200 | 260500316 | 2,720.56 | 260101148 | 2026-02-28 | 2026-04-01 | 2026-04-01 | 135,000 | 2,463.43 | 8 | 260500315 | 2026-05-11 | 72 | 2026-04-08 | Late | Lokal | IDR | BIOTA INDONESIA PT. | S0024 | OPEN | OPEN | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 332,563,050 | 350 | Net 45 | Acuan kurs BI: 16,758 |
| 260100780 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0026 | POTASSIUM FELDSPAR POWDER KN-200 | 260500316 | 2,720.56 | 260101148 | 2026-02-28 | 2026-04-01 | 2026-04-01 | 135,000 | 2,463.43 | 8 | 260401017 | 2026-04-28 | 59 | 2026-04-08 | Late | Lokal | IDR | BIOTA INDONESIA PT. | S0024 | OPEN | OPEN | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 332,563,050 | 350 | Net 45 | Acuan kurs BI: 16,758 |
| 260100780 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0026 | POTASSIUM FELDSPAR POWDER KN-200 | 260500316 | 2,720.56 | 260101148 | 2026-02-28 | 2026-04-01 | 2026-04-01 | 135,000 | 2,463.43 | 8 | 260401054 | 2026-04-29 | 60 | 2026-04-08 | Late | Lokal | IDR | BIOTA INDONESIA PT. | S0024 | OPEN | OPEN | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 332,563,050 | 350 | Net 45 | Acuan kurs BI: 16,758 |
| 260100781 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.005 | COMPOUND FRIT UC 3025 | 260600035 | 8,574.24 | 260101137 | 2026-02-28 | 2026-03-09 | 2026-03-09 | 7,000 | 8,043.84 | 8 | 260300369 | 2026-03-10 | 10 | 2026-03-16 | On time | Lokal | IDR | UNICER INDOASIA, PT | S0522 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 56,306,880 | 0 | Net 60 | Acuan kurs BI: 16,758 |
| 260100782 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0002 | TRANSPARENT FRIT IT-1413A | 260600053 | 10,466.4 | 260101139 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 160,000 | 10,091.4 | 8 | 260300285 | 2026-03-07 | 7 | 2026-04-06 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,614,624,000 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 13/3 (40T) - 31/3 (40T) |
| 260100782 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0002 | TRANSPARENT FRIT IT-1413A | 260600053 | 10,466.4 | 260101139 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 160,000 | 10,091.4 | 8 | 260300372 | 2026-03-10 | 10 | 2026-04-06 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,614,624,000 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 13/3 (40T) - 31/3 (40T) |
| 260100782 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0002 | TRANSPARENT FRIT IT-1413A | 260600053 | 10,466.4 | 260101139 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 160,000 | 10,091.4 | 8 | 260300283 | 2026-03-07 | 7 | 2026-04-06 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,614,624,000 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 13/3 (40T) - 31/3 (40T) |
| 260100782 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0002 | TRANSPARENT FRIT IT-1413A | 260600053 | 10,466.4 | 260101139 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 160,000 | 10,091.4 | 8 | 260300284 | 2026-03-07 | 7 | 2026-04-06 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,614,624,000 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 13/3 (40T) - 31/3 (40T) |
| 260100782 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0002 | TRANSPARENT FRIT IT-1413A | 260600053 | 10,466.4 | 260101139 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 160,000 | 10,091.4 | 8 | 260300609 | 2026-03-14 | 14 | 2026-04-06 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,614,624,000 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 13/3 (40T) - 31/3 (40T) |
| 260100783 | 2026-02-20 | BAHAN BAKU GLAZE | 1099.0019 | KAOLIN NOODLE KS-02 | 260600047 | 2,540 | 260101138 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 50,000 | 2,500 | 8 | 260300317 | 2026-03-09 | 9 | 2026-04-07 | On time | Lokal | IDR | GRAHA JAYA SENTOSA CV. | S0001 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 125,000,000 | 0 | Net 60 | Schedule kedatangan: - 13/3 (25T) - 31/3 (25T) |
| 260100783 | 2026-02-20 | BAHAN BAKU GLAZE | 1099.0019 | KAOLIN NOODLE KS-02 | 260600047 | 2,540 | 260101138 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 50,000 | 2,500 | 8 | 260400379 | 2026-04-11 | 42 | 2026-04-07 | Late | Lokal | IDR | GRAHA JAYA SENTOSA CV. | S0001 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 125,000,000 | 0 | Net 60 | Schedule kedatangan: - 13/3 (25T) - 31/3 (25T) |
| 260100783 | 2026-02-20 | BAHAN BAKU GLAZE | 1099.0019 | KAOLIN NOODLE KS-02 | 260600047 | 2,540 | 260101138 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 50,000 | 2,500 | 8 | – | – | – | 2026-04-07 | Overdue | Lokal | IDR | GRAHA JAYA SENTOSA CV. | S0001 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 125,000,000 | 0 | Net 60 | Schedule kedatangan: - 13/3 (25T) - 31/3 (25T) |
| 260100784 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.001 | TRANSPARENT FRIT XIT-6315 | 260600052 | 6,541.5 | 260101142 | 2026-02-28 | 2026-03-14 | 2026-03-14 | 25,000 | 6,307.13 | 8 | 260300229 | 2026-03-06 | 6 | 2026-03-21 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 157,678,250 | 0 | Net 90 | Acuan kurs bulanan: 16,819 |
| 260100784 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.001 | TRANSPARENT FRIT XIT-6315 | 260600052 | 6,541.5 | 260101142 | 2026-02-28 | 2026-03-14 | 2026-03-14 | 25,000 | 6,307.13 | 8 | 260300370 | 2026-03-10 | 10 | 2026-03-21 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 157,678,250 | 0 | Net 90 | Acuan kurs bulanan: 16,819 |
| 260100785 | 2026-02-20 | BAHAN BAKU GLAZE | 1099.0023 | BENTONITE LGI | 260300141 | 6,750 | 260101147 | 2026-02-28 | 2026-03-11 | 2026-03-11 | 3,000 | 6,750 | 8 | 260300501 | 2026-03-12 | 12 | 2026-03-18 | On time | Lokal | IDR | BIOTA INDONESIA PT. | S0024 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 20,250,000 | 0 | Net 45 | – |
| 260100786 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0018 | COMPOSED GLAZE (MATT) IG-405 | 260600277 | 8,024.24 | 260101140 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 110,000 | 7,736.74 | 8 | 260300596 | 2026-03-14 | 14 | 2026-04-07 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 851,041,400 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 12/3 (30T) |
| 260100786 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0018 | COMPOSED GLAZE (MATT) IG-405 | 260600277 | 8,024.24 | 260101140 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 110,000 | 7,736.74 | 8 | 260300599 | 2026-03-14 | 14 | 2026-04-07 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 851,041,400 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 12/3 (30T) |
| 260100786 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0018 | COMPOSED GLAZE (MATT) IG-405 | 260600277 | 8,024.24 | 260101140 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 110,000 | 7,736.74 | 8 | 260300371 | 2026-03-10 | 10 | 2026-04-07 | On time | Lokal | IDR | CHINA GLAZE INDONESIA PT. | S0009 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 851,041,400 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 05/3 (40T) - 09/3 (40T) - 12/3 (30T) |
| 260100787 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0057 | TRANSPARENT FRIT 1615 | 260600050 | 8,285.9 | 260101127 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 135,000 | 7,989.03 | 8 | 260300107 | 2026-03-04 | 4 | 2026-04-06 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,078,519,050 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 02/03 (50T) - 06/03 (30T) - 10/03 (30T) - 30/03 (25T) |
| 260100787 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0057 | TRANSPARENT FRIT 1615 | 260600050 | 8,285.9 | 260101127 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 135,000 | 7,989.03 | 8 | 260300231 | 2026-03-06 | 6 | 2026-04-06 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,078,519,050 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 02/03 (50T) - 06/03 (30T) - 10/03 (30T) - 30/03 (25T) |
| 260100787 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0057 | TRANSPARENT FRIT 1615 | 260600050 | 8,285.9 | 260101127 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 135,000 | 7,989.03 | 8 | 260300499 | 2026-03-12 | 12 | 2026-04-06 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,078,519,050 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 02/03 (50T) - 06/03 (30T) - 10/03 (30T) - 30/03 (25T) |
| 260100787 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0057 | TRANSPARENT FRIT 1615 | 260600050 | 8,285.9 | 260101127 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 135,000 | 7,989.03 | 8 | 260300498 | 2026-03-12 | 12 | 2026-04-06 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,078,519,050 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 02/03 (50T) - 06/03 (30T) - 10/03 (30T) - 30/03 (25T) |
| 260100787 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0057 | TRANSPARENT FRIT 1615 | 260600050 | 8,285.9 | 260101127 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 135,000 | 7,989.03 | 8 | 260300022 | 2026-03-02 | 2 | 2026-04-06 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,078,519,050 | 0 | Net 90 | Acuan kurs bulanan: 16,819 Schedule kedatangan: - 02/03 (50T) - 06/03 (30T) - 10/03 (30T) - 30/03 (25T) |
| 260100788 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0059 | TITANIUM DIOXIDE ANASTASE DHA-100 | 260600046 | 42,692.57 | 260101141 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 6,000 | 34,521.48 | 8 | 260300652 | 2026-03-16 | 16 | 2026-03-19 | On time | Lokal | IDR | GUNUNG SEMESTA SENTOSA, PT. | S0775 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 207,128,880 | 0 | Net 60 | Acuan kurs BI: 16,758 |
| 260100789 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0056 | TRANSPARENT FRIT YGC 00029 | 260101143 | 8,208 | 260101143 | 2026-02-28 | 2026-03-05 | 2026-03-05 | 20,000 | 8,208 | 8 | 260300230 | 2026-03-06 | 6 | 2026-03-12 | On time | Lokal | IDR | TORRECID INDONESIA, PT | S0516 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 164,160,000 | 0 | Net 90 | – |
| 260100790 | 2026-02-20 | BAHAN BAKU GLAZE | 1020.0019 | OPACIFIER U-10 | 260600040 | 28,580.8 | 260101144 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 50,000 | 26,812.8 | 8 | 260300559 | 2026-03-13 | 13 | 2026-04-07 | On time | Lokal | IDR | PRIMACO PUTRA PERSADA CV. | S0023 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,340,640,000 | 0 | Net 60 | Acuan kurs BI: 16,758 - 06/3 (30T) - 31/3 (20T) |
| 260100790 | 2026-02-20 | BAHAN BAKU GLAZE | 1020.0019 | OPACIFIER U-10 | 260600040 | 28,580.8 | 260101144 | 2026-02-28 | 2026-03-31 | 2026-03-31 | 50,000 | 26,812.8 | 8 | 260300232 | 2026-03-06 | 6 | 2026-04-07 | On time | Lokal | IDR | PRIMACO PUTRA PERSADA CV. | S0023 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 1,340,640,000 | 0 | Net 60 | Acuan kurs BI: 16,758 - 06/3 (30T) - 31/3 (20T) |
| 260100791 | 2026-02-20 | BAHAN BAKU GLAZE | 1020.0023 | HIGH COE TITANIUM FRIT K-0863 | 260600042 | 10,028.75 | 260101132 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 100,000 | 9,463.75 | 8 | 260301016 | 2026-03-31 | 31 | 2026-04-06 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 946,375,000 | 0 | Net 120 | Schedule kedatangan: - 12/3 (40T) - 28/3 (30T) - 31/3 (30T) |
| 260100791 | 2026-02-20 | BAHAN BAKU GLAZE | 1020.0023 | HIGH COE TITANIUM FRIT K-0863 | 260600042 | 10,028.75 | 260101132 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 100,000 | 9,463.75 | 8 | 260300892 | 2026-03-27 | 27 | 2026-04-06 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 946,375,000 | 0 | Net 120 | Schedule kedatangan: - 12/3 (40T) - 28/3 (30T) - 31/3 (30T) |
| 260100791 | 2026-02-20 | BAHAN BAKU GLAZE | 1020.0023 | HIGH COE TITANIUM FRIT K-0863 | 260600042 | 10,028.75 | 260101132 | 2026-02-28 | 2026-03-30 | 2026-03-30 | 100,000 | 9,463.75 | 8 | 260300558 | 2026-03-13 | 13 | 2026-04-06 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 946,375,000 | 0 | Net 120 | Schedule kedatangan: - 12/3 (40T) - 28/3 (30T) - 31/3 (30T) |
| 260100792 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0064 | TRANSPARENT FRIT AR 273 | 260500269 | 9,010.44 | 260101145 | 2026-02-28 | 2026-03-04 | 2026-03-04 | 30,000 | 8,630.37 | 8 | 260300182 | 2026-03-05 | 5 | 2026-03-11 | On time | Lokal | IDR | ARROW INDO UNIVERSAL, PT. | S0801 | OPEN | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | – | 258,911,100 | 0 | Net 60 | Acuan kurs BI: 16.758 |
| 260100793 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0063 | TRANSPARENT FRIT FJ 9828 B | 260600080 | 9,333 | 260101146 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 15,000 | 8,998 | 8 | 260300854 | 2026-03-26 | 26 | 2026-03-19 | Late | Lokal | IDR | YOUNEXA MATERIALS UTAMA PT. | S0022 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 134,970,000 | 0 | Net 120 | – |
| 260100793 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0063 | TRANSPARENT FRIT FJ 9828 B | 260600080 | 9,333 | 260101146 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 15,000 | 8,998 | 8 | 260300318 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | YOUNEXA MATERIALS UTAMA PT. | S0022 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 134,970,000 | 0 | Net 120 | – |
| 260100794 | 2026-02-20 | BAHAN BAKU GLAZE | 1030.0062 | TRANSPARENT FRIT K 0248 | 260600043 | 8,786.25 | 260101133 | 2026-02-28 | 2026-03-13 | 2026-03-13 | 25,000 | 8,291.25 | 8 | 260300316 | 2026-03-09 | 9 | 2026-03-20 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | CLOSED | CLOSED | 2026-02-27 | Moch Firdaus Fasa Zulfikiri | KG | 207,281,250 | 0 | Net 120 | – |
| 260100799 | 2026-02-23 | PERSEDIAAN UMUM | 6050.1374 | PELAMPUNG SOLAR 3/4 INCH | 260101171 | 82,000 | 260101171 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 2 | 82,000 | 5 | 260300060 | 2026-03-04 | 4 | 2026-03-23 | On time | Lokal | IDR | CENTRAL NUSA JAYA .PT | S0825 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 164,000 | 0 | Net 30 | GENSET PN1 & PN2 |
| 260100801 | 2026-02-23 | SPAREPART | 5019.0096 | GEAR REDUCER MNRV 063 1:20 | 260300406 | 4,500,000 | 260101131 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 2 | 4,500,000 | 5 | 260300234 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | MULTI TEKNIK TELAGA INDONESIA PT. | S0415 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 9,000,000 | 0 | Net 30 | OUT HD PN2 & GLAZING LINE PN2. MOTOVARIO |
| 260100801 | 2026-02-23 | SPAREPART | 5019.0111 | GEAR REDUCER MNRV 063 R 1:30 (FLANGE 0.75 KW B14) | 260500193 | 4,500,000 | 260101131 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 3 | 4,500,000 | 5 | 260300234 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | MULTI TEKNIK TELAGA INDONESIA PT. | S0415 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 13,500,000 | 0 | Net 30 | OUT HD PN2 & GLAZING LINE PN2. MOTOVARIO |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0037 | V. BELT B - 53 | 260101176 | 38,500 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 4 | 38,500 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 154,000 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0036 | V. BELT B - 50 | 260500209 | 39,900 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 4 | 36,300 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 145,200 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0041 | V. BELT B - 60 | 260101176 | 43,600 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 6 | 43,600 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 261,600 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0044 | V. BELT B - 64 | 260500468 | 51,050 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 4 | 46,500 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 186,000 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0145 | V. BELT C - 177 | 260101176 | 238,600 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 4 | 238,600 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 954,400 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0143 | V. BELT C - 150 | 260101176 | 202,200 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 3 | 202,200 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 606,600 | 0 | Net 60 | STOK WRM |
| 260100804 | 2026-02-23 | SPAREPART | 5021.0332 | V. BELT C - 236 | 260101176 | 328,500 | 260101176 | 2026-02-28 | 2026-03-16 | 2026-03-16 | 6 | 328,500 | 5 | 260300266 | 2026-03-06 | 6 | 2026-03-23 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 1,971,000 | 0 | Net 60 | STOK WRM |
| 260100808 | 2026-02-23 | PERSEDIAAN UMUM | 6050.1378 | FOOT KLEP FULL KUNINGAN | 260101177 | 709,459.46 | 260101177 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 5 | 709,459.46 | 5 | 260300135 | 2026-03-04 | 4 | 2026-03-19 | On time | Lokal | IDR | SUMBER ABADI CV | S0665 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 3,547,297.3 | 0 | Net 30 | TANDON AIR PN2. SAILING MODEL GEMBUNG. FULL KUNINGAN |
| 260100808 | 2026-02-23 | PERSEDIAAN UMUM | 6050.1378 | FOOT KLEP FULL KUNINGAN | 260101177 | 709,459.46 | 260101177 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 5 | 709,459.46 | 5 | 260300696 | 2026-03-16 | 16 | 2026-03-19 | On time | Lokal | IDR | SUMBER ABADI CV | S0665 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 3,547,297.3 | 0 | Net 30 | TANDON AIR PN2. SAILING MODEL GEMBUNG. FULL KUNINGAN |
| 260100810 | 2026-02-24 | SPAREPART | 5017.0469 | CONTAC AUXILARY SIEMENS NC 3RH 2911 - 1HA22 | 260101104 | 127,000 | 260101104 | 2026-02-28 | 2026-03-05 | 2026-03-05 | 20 | 127,000 | 4 | 260300108 | 2026-03-04 | 4 | 2026-03-12 | On time | Lokal | IDR | SINERGI INTEGRA PERSADA PT. | S0419 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 2,540,000 | 0 | Net 7 | PRESS 2B & PRESS 1C. URGENT |
| 260100810 | 2026-02-24 | SPAREPART | 5017.047 | CONTACTOR SIEMENS 3RT2023 - 1BB40 | 260101104 | 678,000 | 260101104 | 2026-02-28 | 2026-03-05 | 2026-03-05 | 20 | 678,000 | 4 | 260300108 | 2026-03-04 | 4 | 2026-03-12 | On time | Lokal | IDR | SINERGI INTEGRA PERSADA PT. | S0419 | CLOSED | CLOSED | 2026-02-28 | Gita | PCS | 13,560,000 | 0 | Net 7 | PRESS 2B & PRESS 1C. URGENT |
| 260100811 | 2026-02-24 | PERSEDIAAN UMUM | 6030.2564 | PLAT BAJA STRIP 9.8X5.8X5400 MM | 260101168 | 252,252.25 | 260101168 | 2026-02-28 | 2026-03-09 | 2026-03-09 | 1 | 252,252.25 | 4 | 260300246 | 2026-03-06 | 6 | 2026-03-16 | On time | Lokal | IDR | SUMBER ABADI BAJA PERKASA CV. | S0074 | CLOSED | CLOSED | 2026-02-28 | Gita | BTG | 252,252.25 | 0 | Net 30 | PEMBUATAN STOPER OUT KILN 1C |
| 260100836 | 2026-02-24 | PERSEDIAAN UMUM | 6020.0371 | SAKLAR SERI SCHNEIDER VIVACE | 260101158 | 125,000 | 260101158 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 5 | 125,000 | 4 | 260300258 | 2026-03-06 | 6 | 2026-03-07 | On time | Lokal | IDR | SAMUDRA ARUNG NUSANTARA. PT | S0738 | CLOSED | CLOSED | 2026-03-01 | Gita | PCS | 625,000 | 0 | Net 30 | OFFICE SHOWROOM |
| 260100838 | 2026-02-24 | BAHAN PEMBANTU | 20OT.0001 | PAC POWDER | 260400507 | 9,000 | 260101151 | 2026-02-28 | 2026-03-06 | 2026-03-06 | 4,000 | 9,000 | 4 | 260300495 | 2026-03-12 | 12 | 2026-03-13 | On time | Lokal | IDR | PRIMACO PUTRA PERSADA CV. | S0023 | CLOSED | CLOSED | 2026-03-03 | Moch Firdaus Fasa Zulfikiri | KG | 36,000,000 | 0 | Net 60 | – |
| 260100838 | 2026-02-24 | BAHAN PEMBANTU | 20OT.0001 | PAC POWDER | 260400507 | 9,000 | 260101151 | 2026-02-28 | 2026-03-06 | 2026-03-06 | 4,000 | 9,000 | 4 | 260300180 | 2026-03-05 | 5 | 2026-03-13 | On time | Lokal | IDR | PRIMACO PUTRA PERSADA CV. | S0023 | CLOSED | CLOSED | 2026-03-03 | Moch Firdaus Fasa Zulfikiri | KG | 36,000,000 | 0 | Net 60 | – |
| 260100840 | 2026-02-24 | BAHAN BAKU GLAZE | 1099.0007 | ENGOBE UNDER TILE WE-80 | 260600082 | 3,400 | 260101149 | 2026-02-28 | 2026-03-04 | 2026-03-04 | 10,000 | 3,400 | 4 | 260300178 | 2026-03-05 | 5 | 2026-03-11 | On time | Lokal | IDR | LINOCO SURYA ABADI PT. | S0015 | CLOSED | CLOSED | 2026-03-03 | Moch Firdaus Fasa Zulfikiri | KG | 34,000,000 | 0 | Net 60 | – |
| 260100841 | 2026-02-24 | BAHAN BAKU GLAZE | 1098.0006 | PS-8000 | 260600276 | 20,060.6 | 260101150 | 2026-02-28 | 2026-03-05 | 2026-03-05 | 5,000 | 18,500.9 | 4 | 260300110 | 2026-03-04 | 4 | 2026-03-12 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-03-03 | Moch Firdaus Fasa Zulfikiri | KG | 92,504,500 | 0 | Net 90 | Acuan kurs bulanan: 16,819 |
| 260100844 | 2026-02-25 | PERSEDIAAN UMUM | 6030.0004 | SEMEN GRESIK 40KG | 260500241 | 59,500 | 260101156 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 30 | 58,000 | 3 | 260300066 | 2026-03-04 | 4 | 2026-03-07 | On time | Lokal | IDR | UD. MIRA MAKMUR | S0174 | CLOSED | CLOSED | 2026-03-03 | Gita | SAK | 1,740,000 | 0 | Net 60 | UNTUK PEKERJAAN PAVING DAN GLAZING LINE AREA PN2 |
| 260100852 | 2026-02-25 | SPAREPART | 5019.0006 | MOTOR 0.37KW 0.5HP 1460 RPM 380V FLANGE B5 | 260500136 | 875,000 | 260101167 | 2026-02-28 | 2026-03-11 | 2026-03-11 | 2 | 875,000 | 3 | 260300141 | 2026-03-04 | 4 | 2026-03-18 | On time | Lokal | IDR | MULTI TEKNIK TELAGA INDONESIA PT. | S0415 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 1,750,000 | 0 | Net 30 | STOK WHSP |
| 260100853 | 2026-02-25 | SPAREPART | 5025.0014 | SELENOID VALVE UNI D 220V | 260400291 | 355,000 | 260101114 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 8 | 355,000 | 3 | 260300079 | 2026-03-04 | 4 | 2026-03-19 | On time | Lokal | IDR | PUTRA ANDALAN SAKTI PT. | S0139 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 2,840,000 | 0 | Net 60 | STOK WHSP |
| 260100856 | 2026-02-25 | SPAREPART | 5020.0007 | ADAPTER H-2315 | 260101122 | 100,000 | 260101122 | 2026-02-28 | 2026-03-11 | 2026-03-11 | 5 | 100,000 | 3 | 260300155 | 2026-03-04 | 4 | 2026-03-18 | On time | Lokal | IDR | CENTURY BEARINDO PT. (PPN) | S0043 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 500,000 | 0 | Net 60 | STOK WHSP. FBJ |
| 260100857 | 2026-02-25 | SPAREPART | 5012.0202 | SEAL TC 45.65.7 | 260101117 | 9,000 | 260101117 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 15 | 9,000 | 3 | 260300267 | 2026-03-06 | 6 | 2026-03-19 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 135,000 | 0 | Net 60 | STOK WHSP. TTO |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.021 | MUR M 14 | 260500464 | 1,050 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 975 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 97,500 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0208 | MUR M 10 | 260500464 | 450 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 425 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 21,250 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0207 | MUR M 8 | 260500464 | 150 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 145 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 14,500 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0206 | MUR M 6 | 260500464 | 95 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 95 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 9,500 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.022 | MUR M 5 | 260400531 | 45 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 45 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 4,500 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0211 | MUR M 16 | 260500464 | 1,400 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 1,330 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 133,000 | 0 | Net 30 | STOK WHSP |
| 260100858 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0145 | MUR M 22 | 260300185 | 3,415 | 260101173 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 3,415 | 3 | 260300360 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 170,750 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0239 | RING PLAT M-16 | 260500464 | 605 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 605 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 60,500 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0244 | RING PLAT M-20 | 260600169 | 1,210 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 1,210 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 60,500 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0237 | RING PLAT M 12 | 260500464 | 260 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 150 | 260 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 39,000 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0236 | RING PLAT M-10 | 260500464 | 145 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 150 | 145 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 21,750 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0235 | RING PLAT M-8 | 260500464 | 90 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 150 | 90 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 13,500 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0234 | RING PLAT M-6 | 260500464 | 90 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 90 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 9,000 | 0 | Net 30 | STOK WHSP |
| 260100859 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0232 | RING PLAT M-4 | 260400531 | 60 | 260101174 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 60 | 3 | 260300359 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 6,000 | 0 | Net 30 | STOK WHSP |
| 260100860 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0027 | BAUT M-16*70 | 260101172 | 3,250 | 260101172 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 3,250 | 3 | 260300361 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 162,500 | 0 | Net 30 | STOK WHSP |
| 260100860 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0008 | BAUT M-6*30 | 260500465 | 255 | 260101172 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 210 | 3 | 260300361 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 21,000 | 0 | Net 30 | STOK WHSP |
| 260100860 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0087 | BAUT M 16 X 60 | 260600061 | 3,680 | 260101172 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 2,965 | 3 | 260300361 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 148,250 | 0 | Net 30 | STOK WHSP |
| 260100860 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0652 | BAUT M 8X20 | 260101172 | 315 | 260101172 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 315 | 3 | 260300361 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 31,500 | 0 | Net 30 | STOK WHSP |
| 260100860 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0075 | BAUT M 6X20 | 260500465 | 215 | 260101172 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 100 | 175 | 3 | 260300361 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 17,500 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.005 | BAUT L M 10X40 | 260500465 | 1,640 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 2,000 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 100,000 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0045 | BAUT L M 8*30 | 260400525 | 985 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 30 | 985 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 29,550 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0054 | BAUT L M 12*50 | 260400300 | 3,250 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 3,250 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 162,500 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.012 | BAUT L M 8X25 | 260400525 | 900 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 30 | 900 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 27,000 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0441 | BAUT L M 5X20 | 260600169 | 320 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 355 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 17,750 | 0 | Net 30 | STOK WHSP |
| 260100861 | 2026-02-25 | PERSEDIAAN UMUM | 6060.0053 | BAUT L M 12X20 | 260400525 | 2,200 | 260101121 | 2026-02-28 | 2026-03-12 | 2026-03-12 | 50 | 2,200 | 3 | 260300363 | 2026-03-09 | 9 | 2026-03-19 | On time | Lokal | IDR | AGUNG JAYA BAUT | S0196 | OPEN | CLOSED | 2026-03-03 | Gita | PCS | 110,000 | 0 | Net 30 | STOK WHSP |
| 260100869 | 2026-02-25 | PERSEDIAAN UMUM | 6060.034 | SPEI 8 | 260400530 | 9,000 | 260101118 | 2026-02-28 | 2026-03-11 | 2026-03-11 | 10 | 9,000 | 3 | 260300272 | 2026-03-06 | 6 | 2026-03-18 | On time | Lokal | IDR | ASIAN BERINDO JAYA PT. | S0037 | CLOSED | CLOSED | 2026-03-03 | Gita | PCS | 90,000 | 0 | Net 60 | STOK WHSP. LK |
| 260100872 | 2026-02-25 | PERSEDIAAN UMUM | 6020.0056 | PENETRATING OIL ER 5711 | 260500455 | 54,500 | 260101119 | 2026-02-28 | 2026-03-07 | 2026-03-07 | 36 | 49,500 | 3 | 260300087 | 2026-03-04 | 4 | 2026-03-14 | On time | Lokal | IDR | KAWAN LAMA JAYA CV. | S0125 | CLOSED | CLOSED | 2026-03-03 | Gita | CAN | 1,782,000 | 0 | Net 60 | STOK WHSP |
| 260100872 | 2026-02-25 | PERSEDIAAN UMUM | 6020.0056 | PENETRATING OIL ER 5711 | 260500455 | 54,500 | 260101119 | 2026-02-28 | 2026-03-07 | 2026-03-07 | 36 | 49,500 | 3 | – | – | – | 2026-03-14 | Overdue | Lokal | IDR | KAWAN LAMA JAYA CV. | S0125 | CLOSED | CLOSED | 2026-03-03 | Gita | CAN | 1,782,000 | 0 | Net 60 | STOK WHSP |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2762 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=3.1 M | 260600067 | 361,457.21 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 264,533.33 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 529,066.67 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.1847 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=1,7 M | 260101157 | 145,066.67 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 145,066.67 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 290,133.33 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.276 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=2 M | 260101157 | 170,666.67 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 170,666.67 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 341,333.33 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.1846 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=2,10 M | 260300097 | 179,200 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 8 | 179,200 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 1,433,600 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2757 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=0.9 M | 260101157 | 76,800 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 3 | 76,800 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 230,400 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2758 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=1.2 M | 260101157 | 102,400 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 102,400 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 204,800 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2759 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=1.5 M | 260101157 | 128,000 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 128,000 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 256,000 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.185 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=2,9 M | 260600067 | 338,137.39 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 247,466.67 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 494,933.33 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.1851 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=3,4 M | 260101157 | 290,133.33 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 290,133.33 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 580,266.67 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2763 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=3.6 M | 260101157 | 307,200 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 307,200 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 614,400 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2678 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE= 1050 MM P= 2,6 M | 260101157 | 221,866.67 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 221,866.67 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 443,733.33 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |
| 260100879 | 2026-02-25 | PERSEDIAAN UMUM | 6030.2761 | DR. SHIELD SHEET SINGLE WALL RF1050 WHITE LE=1050MM P=2.3 M | 260101157 | 196,266.67 | 260101157 | 2026-02-28 | 2026-02-28 | 2026-02-28 | 2 | 196,266.67 | 3 | 260300335 | 2026-03-09 | 9 | 2026-03-07 | Late | Lokal | IDR | RAGAM TANGGUH FORTINDO PT. | S0255 | OPEN | CLOSED | 2026-03-03 | Gita | LBR | 392,533.33 | 0 | Net 60 | CLADDING DAN DINDING LOADING DOCK GUDANG 93 |