Consolidated data
LEAD TIME (PR → PO → GRPO) + realisasi, enriched with PO REPORT fields (currency, Lokal/Impor, vendor…) on the right · hover any column header (ⓘ) for its source · 13,431 row(s)
How the files are consolidated— click to expand
Report months follow the procurement cycle, not the calendar: report month M draws data from the 21st of (M-2) through the 20th of (M-1). For example January = 21 Nov–20 Dec, February = 21 Dec–20 Jan. KPI 1/2/3 window on PO date, KPI 4 on PR date, KPI 7 on vendor creation date.
LEAD TIME is the master sheet (PR → PO → GRPO, one row per PR-line, including PRs not yet converted to a PO). It sets the dashboard's date span, is KPI 4's denominator, and carries the goods-receipt detail: GR date and quantity, the ordered PO quantity, the PO Due Date (ETA), last/current price and PR→PO days.
PO REPORT enriches it with the PO detail that LEAD TIME lacks: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), plus ETA, currency and unit price, joined on PO No.
VENDOR LIST is the vendor master; KPI 7 counts Active vendors whose creation date falls in the window (cumulative per year, target 6).
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality) and 6 (Substitution) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR Noⓘ | PR Dateⓘ | Item Groupⓘ | Item Codeⓘ | Itemⓘ | Last POⓘ | Last Priceⓘ | PO Noⓘ | PO Date ▲ⓘ | ETAⓘ | ETA (PO Report)ⓘ | Qtyⓘ | Priceⓘ | PR→POⓘ | GRPO Noⓘ | GRPO Dateⓘ | PO→GRPOⓘ | Deadlineⓘ | Realisasiⓘ | L/Iⓘ | Currencyⓘ | Vendorⓘ | Vendor Codeⓘ | Status PRⓘ | Status POⓘ | Required Dateⓘ | Request Byⓘ | UoMⓘ | Total POⓘ | Outstandingⓘ | TOPⓘ | Remarksⓘ |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 251200295 | 2025-12-17 | SPAREPART | 5030.0122 | SIMPLE CHAIN P=1/2" C9990011025 | 260100054 | 752,386 | 260100054 | 2026-01-06 | 2026-01-22 | 2026-01-22 | 4 | 752,386 | 20 | 260100649 | 2026-01-20 | 14 | 2026-01-29 | On time | Lokal | IDR | SYSTEM INDONESIA PT. | S0367 | CLOSED | CLOSED | 2026-02-02 | Nanda Ayu Pratiwi | MTR | 3,009,544 | 0 | Net 60 | PACKING PN 1 |
| 251200295 | 2025-12-17 | SPAREPART | 5030.1552 | ECCENTRIX CENTERING GUIDE C9213502202 | 260100054 | 878,956 | 260100054 | 2026-01-06 | 2026-01-22 | 2026-01-22 | 10 | 878,956 | 20 | 260300412 | 2026-03-10 | 63 | 2026-01-29 | Late | Lokal | IDR | SYSTEM INDONESIA PT. | S0367 | CLOSED | CLOSED | 2026-02-02 | Nanda Ayu Pratiwi | PCS | 8,789,560 | 0 | Net 60 | PACKING PN 1 |
| 251200295 | 2025-12-17 | SPAREPART | 5030.1553 | CONCENTRIX CENTERING GUIDE C9213502201 | 260100054 | 829,734 | 260100054 | 2026-01-06 | 2026-01-22 | 2026-01-22 | 6 | 829,734 | 20 | 260101714 | 2026-02-18 | 43 | 2026-01-29 | Late | Lokal | IDR | SYSTEM INDONESIA PT. | S0367 | CLOSED | CLOSED | 2026-02-02 | Nanda Ayu Pratiwi | PCS | 4,978,404 | 0 | Net 60 | PACKING PN 1 |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101187 | 2026-02-04 | 29 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100274 | 2026-01-09 | 3 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100226 | 2026-01-08 | 2 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100813 | 2026-01-23 | 17 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100717 | 2026-01-22 | 16 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100414 | 2026-01-13 | 7 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100315 | 2026-01-12 | 6 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100568 | 2026-01-19 | 13 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101845 | 2026-02-21 | 46 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100929 | 2026-01-27 | 21 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | – | – | – | 2026-01-22 | Overdue | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100778 | 2026-01-23 | 17 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100674 | 2026-01-21 | 15 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100621 | 2026-01-20 | 14 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100483 | 2026-01-15 | 9 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101130 | 2026-01-31 | 25 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100512 | 2026-01-15 | 9 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100984 | 2026-01-28 | 22 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101044 | 2026-01-29 | 23 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101110 | 2026-01-31 | 25 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100887 | 2026-01-26 | 20 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100361 | 2026-01-13 | 7 | 2026-01-22 | On time | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101630 | 2026-02-16 | 41 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260100854 | 2026-01-26 | 20 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200401 | 2025-12-23 | BAHAN BAKU BODY | 1010.0022 | PHIROPILIT (ANUGERAH) | 260600006 | 218 | 260100049 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 2,800,000 | 196 | 14 | 260101165 | 2026-02-03 | 28 | 2026-01-22 | Late | Lokal | IDR | CV. ANUGERAH TAMBANG | S0540 | CLOSED | OPEN | 2025-12-29 | Qhadafy | KG | 548,800,000 | 20,070 | Net 45 | – |
| 251200427 | 2025-12-26 | SPAREPART | 5011.0031 | BEARING 30304 | 260300183 | 65,000 | 260100052 | 2026-01-06 | 2026-01-17 | 2026-01-17 | 10 | 65,000 | 11 | 260100389 | 2026-01-13 | 7 | 2026-01-24 | On time | Lokal | IDR | CENTURY BEARINDO PT. (PPN) | S0043 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 650,000 | 0 | Net 60 | GEARBOX CONVEYOR. FAG |
| 251200427 | 2025-12-26 | SPAREPART | 5011.0031 | BEARING 30304 | 260300183 | 65,000 | 260100052 | 2026-01-06 | 2026-01-17 | 2026-01-17 | 10 | 65,000 | 11 | 260100386 | 2026-01-13 | 7 | 2026-01-24 | On time | Lokal | IDR | CENTURY BEARINDO PT. (PPN) | S0043 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 650,000 | 0 | Net 60 | GEARBOX CONVEYOR. FAG |
| 251200427 | 2025-12-26 | SPAREPART | 5011.0022 | BEARING 30205 | 260100052 | 70,000 | 260100052 | 2026-01-06 | 2026-01-17 | 2026-01-17 | 10 | 70,000 | 11 | 260100389 | 2026-01-13 | 7 | 2026-01-24 | On time | Lokal | IDR | CENTURY BEARINDO PT. (PPN) | S0043 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 700,000 | 0 | Net 60 | GEARBOX CONVEYOR. FAG |
| 251200427 | 2025-12-26 | SPAREPART | 5011.0025 | BEARING 30208 | 260400011 | 98,900 | 260100052 | 2026-01-06 | 2026-01-17 | 2026-01-17 | 5 | 100,000 | 11 | 260100389 | 2026-01-13 | 7 | 2026-01-24 | On time | Lokal | IDR | CENTURY BEARINDO PT. (PPN) | S0043 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 500,000 | 0 | Net 60 | GEARBOX CONVEYOR. FAG |
| 251200427 | 2025-12-26 | SPAREPART | 5017.0128 | OMRON RELAY G2R/24 VD | 260100053 | 54,000 | 260100053 | 2026-01-06 | 2026-01-26 | 2026-01-26 | 10 | 54,000 | 11 | 260100554 | 2026-01-17 | 11 | 2026-02-02 | On time | Lokal | IDR | MITRAINTI SEJAHTERA ELETRINDO PT. | S0040 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 540,000 | 0 | Net 30 | SPARE RELAY HD 1C |
| 251200427 | 2025-12-26 | SPAREPART | 5017.0055 | FUJI MAGNETIC CONTACTOR SC N1/220 V | 260400174 | 645,000 | 260100043 | 2026-01-06 | 2026-01-26 | 2026-01-26 | 5 | 535,000 | 11 | 260100520 | 2026-01-15 | 9 | 2026-02-02 | On time | Lokal | IDR | SAMUDRA ARUNG NUSANTARA. PT | S0738 | CLOSED | CLOSED | 2026-01-02 | Nanda Ayu Pratiwi | PCS | 2,675,000 | 0 | Net 30 | MOTOR KECIL BALLMILL |
| 251200438 | 2025-12-27 | BAHAN PACKING | 3011.0233 | BOX KOBIN BK TS KW 1 50X50 | 260600120 | 1,459 | 260100050 | 2026-01-06 | 2026-01-24 | 2026-01-24 | 33,600 | 1,227 | 10 | 260100493 | 2026-01-15 | 9 | 2026-01-31 | On time | Lokal | IDR | SARANA PACKAGING AGRAPANA PT. | S0477 | CLOSED | CLOSED | 2025-12-29 | Qhadafy | PCS | 41,227,200 | 0 | Net 60 | – |
| 251200439 | 2025-12-30 | BAHAN PEMBANTU | 20BK.0015 | MEDIUM ALUMINA LINING BRICK 140X40X97 | 260500418 | 0.36 | 260100034 | 2026-01-06 | 2026-02-10 | 2026-02-10 | 29,000 | 0.506 | 7 | 260101626 | 2026-02-16 | 41 | 2026-02-17 | On time | Impor | USD | SHANDONG VICTOR ADVANCED MATERIAL TECHNOLOGY CO., LTD. | S0583 | CLOSED | CLOSED | 2026-01-20 | Gandhi | PCS | 245,760,152 | 0 | Net 60 | BALLMILL |
| 251200439 | 2025-12-30 | BAHAN PEMBANTU | 20BK.0016 | MEDIUM ALUMINA LINING BRICK 140X40x40X97 | 260300203 | 0.45 | 260100034 | 2026-01-06 | 2026-02-10 | 2026-02-10 | 21,000 | 0.506 | 7 | 260101626 | 2026-02-16 | 41 | 2026-02-17 | On time | Impor | USD | SHANDONG VICTOR ADVANCED MATERIAL TECHNOLOGY CO., LTD. | S0583 | CLOSED | CLOSED | 2026-01-20 | Gandhi | PCS | 177,964,248 | 0 | Net 60 | BALLMILL |
| 251200446 | 2025-12-30 | BAHAN BAKU GLAZE | 1099.0018 | BALLCLAY (NOODLE) OPAL KA | 260600037 | 1,311 | 260100082 | 2026-01-06 | 2026-01-15 | 2026-01-15 | 24,000 | 1,200 | 7 | 260100978 | 2026-01-28 | 22 | 2026-01-22 | Late | Lokal | IDR | SIBELCO LAUTAN MINERALS PT. | S0003 | OPEN | CLOSED | 2026-01-12 | Moch Firdaus Fasa Zulfikiri | KG | 28,800,000 | 0 | Net 60 | – |
| 251200447 | 2025-12-30 | BAHAN BAKU GLAZE | 1098.0014 | STPP (Sodium Tripolyphospate) | 260600045 | 25,700 | 260100081 | 2026-01-06 | 2026-01-14 | 2026-01-14 | 9,000 | 23,000 | 7 | 260100416 | 2026-01-13 | 7 | 2026-01-21 | On time | Lokal | IDR | HARAPAN KIMIA INDONESIA, CV. | S0582 | CLOSED | CLOSED | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 207,000,000 | 0 | Net 45 | – |
| 251200447 | 2025-12-30 | BAHAN BAKU GLAZE | 1098.0014 | STPP (Sodium Tripolyphospate) | 260600045 | 25,700 | 260100081 | 2026-01-06 | 2026-01-14 | 2026-01-14 | 9,000 | 23,000 | 7 | 260100713 | 2026-01-22 | 16 | 2026-01-21 | Late | Lokal | IDR | HARAPAN KIMIA INDONESIA, CV. | S0582 | CLOSED | CLOSED | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 207,000,000 | 0 | Net 45 | – |
| 251200448 | 2025-12-30 | BAHAN BAKU GLAZE | 1098.0004 | CMC C-20 | 260600049 | 85,475.6 | 260100058 | 2026-01-06 | 2026-01-09 | 2026-01-09 | 1,800 | 81,751.6 | 7 | 260100370 | 2026-01-13 | 7 | 2026-01-16 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 147,152,880 | 0 | Net 90 | Acuan kurs bulanan: 16,648 |
| 251200449 | 2025-12-30 | BAHAN BAKU GLAZE | 1099.0024 | ALUMINA A-10 | 260600048 | 12,036.36 | 260100057 | 2026-01-06 | 2026-01-09 | 2026-01-09 | 35,000 | 11,511.96 | 7 | 260100289 | 2026-01-10 | 4 | 2026-01-16 | On time | Lokal | IDR | CERACHEMI INTERNATIONAL PT. | S0008 | CLOSED | CLOSED | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 402,918,600 | 0 | Net 90 | Acuan kurs bulanan: 16,684 |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | – | – | – | 2026-01-27 | Overdue | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100424 | 2026-01-13 | 7 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100524 | 2026-01-15 | 9 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | – | – | – | 2026-01-27 | Overdue | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100533 | 2026-01-17 | 11 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100534 | 2026-01-17 | 11 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100628 | 2026-01-20 | 14 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |
| 251200450 | 2025-12-30 | BAHAN BAKU GLAZE | 1030.0025 | TITANIUM FRIT K - 0810 | 260600041 | 7,898.75 | 260100074 | 2026-01-06 | 2026-01-20 | 2026-01-20 | 240,000 | 7,342.5 | 7 | 260100627 | 2026-01-20 | 14 | 2026-01-27 | On time | Lokal | IDR | KASMAJI INTI UTAMA PT. | S0014 | OPEN | OPEN | 2026-01-14 | Moch Firdaus Fasa Zulfikiri | KG | 1,762,200,000 | 40,000 | Net 120 | Delivery schedule: - 08/01 (40 Ton) - 10/01 (40 Ton) - 13/01 (40 Ton) - 15/01 (40 Ton) - 17/01 (40 Ton) - 19/01 (40 Ton) |