Merged data
The merged procurement sheet (PR → PO → GRPO) with the realisasi status used by KPI 2/3 · 13,488 row(s)
How the three files are consolidated— click to expand
Three SAP exports are combined. The SPINE is PR TO PO TO GRPO — the master PR list (one row per PR-item, including PRs not yet converted to a PO). It sets the dashboard's date span and is KPI 4's denominator.
PO.csv enriches it with the PO details that only it carries: the Lokal/Impor flag (the KPI 2 vs KPI 3 split), the ETA, currency and unit price, joined on PO No.
LEAD TIME PR TO GR adds the goods-receipt detail: one row per GR with its date and quantity, plus the ordered PO quantity, last/current price and PR→PO days. This is what makes the quantity-aware completion possible.
KPI 2/3 'received' logic is quantity-aware: a PO-item counts as received only when the running sum of GR quantities reaches the ordered quantity; the completion date (the GR that crosses the ordered qty) is compared to ETA + 7 days (Local) / 14 days (Import).
On import each file is upserted by its natural key, so re-uploading an updated export updates rows in place instead of duplicating them. KPI 5 (Quality), 6 (Substitution) and 7 (New Vendor) have no source in these files yet — they are seeded with best-case defaults so the scorecard is complete; replace those entries as real data arrives.
Realisasi here uses a 7-day tolerance (local). Each KPI's own formula is on its methodology page — click any KPI title on the dashboard.
| PR No | PR Date | Item Group | Item Code | Item | Last PO | Last Price | PO No | PO Date ▲ | ETA | Qty | Price | PR→PO | GRPO No | GRPO Date | PO→GRPO | Deadline | Realisasi |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 251210045 | 2025-12-05 | 13 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 251210043 | 2025-12-05 | 13 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110045 | 2026-01-06 | 45 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 251210029 | 2025-12-02 | 10 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110046 | 2026-01-06 | 45 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110259 | 2026-01-14 | 53 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110586 | 2026-02-02 | 72 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110567 | 2026-01-31 | 70 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 251210156 | 2025-12-08 | 16 | 2025-11-29 | Late |
| 251110074 | 2025-11-21 | BAHAN BAKU BODY | 1010.0035 | BENTONIT BTCL-2 | 251110134 | 445 | 251110134 | 2025-11-22 | 2025-11-22 | 6,000,000 | 445 | 1 | 260110355 | 2026-01-20 | 59 | 2025-11-29 | Late |